Case Study – Securing National Grid ESO Connections for Everwell Regional Data Centres
Posted on 02 Aug 2024
Background
Everwell Development Limited has embarked on constructing four high-capacity data centres across key locations in the UK. A critical need for these hyperscale data centres is reliable and efficient grid connections. The data centre developer partnered with RE24 Limited to securing National Grid ESO connections aiming for a seamless integration of these data centres into the national grid.
This case study outlines the details of RE24’s consultancy services and support in securing grid connections.
Challange
With four sites capable of supporting 200 MW hyperscale data centres. Everwell Development is looking for transmission-connected grid connections. Each data centre is expecting to get grid connections in Q2 2026.
The primary goal is to secure transmission grid connections for these data centres, which are crucial for supporting the rapid growth in data usage and fostering economic development in these regions.
Our Solutions to Secure National Grid ESO Connection
Establishing the grid connections for the data centres is the key responsibility for RE24. In addition, we offer consultancy services on data centre power requirements and grid connections as well.
- Submission of National Grid ESO Connection Pre-Applications: The steps involved with submission include;
Early engagement with ESO’s Connections Team to discuss the project specifications.
Coordinate with specialist contractors to conduct optional studies assessing the feasibility of the proposed connections, with costs agreed upon for client pass-through.
Arrange and attend pre-application meetings with ESO to clarify requirements and address initial queries. - Submission of National Grid ESO Grid Applications (subject to client investor approvals): Submit the formal application to ESO with detailed technical and financial information. Obtain comprehensive documentation required for the grid application, including site plans, project details, and supporting technical studies. This involves preparing documents on:
– Data centres electrical system layout (single line diagrams, etc.)
– Details of the data centre project system at the transmission site
– Reactive compensation information
– Substation infrastructure
– Circuit parameters - Post-application coordination: Once grid applications are submitted, RE24 will liaise with the National Grid ESO throughout the application process, including the offer and acceptance stages. RE24 will act as the primary point of contact for ESO during this process.
Wins for Everwell
In addition to the secured grid connections for the hyperscale data centres, RE24 will consultation on every step on the application process along with the financial and regulatory feasibilities. As a result, Everwell will get information on the following aspects.
- All possible connection solutions and associated connection dates
- Detailed processes and timescales for each stage conducted by NGET/ESO
- High-level connection budgets for the sites
- Spatial requirements for on-site equipment
This ongoing partnership between Everwell Development and RE24 demonstrates a proactive approach taken to meet the growing demands of the data centre industry. In order to facilitate the sustainable expansion of the UK’s data infrastructure, Everwell hopes to secure prompt and effective grid connections from National Grid ESO. Team RE24, coming from more than 18 years’ experience in UK energy sector will help Everwell in reaching grid connection milestones.