CBAM's New PPA Rules for 2026

Published on 26 January 2026

Himaya Sewwandi - RE24

Himaya Sewwandi
Project Manager

The European Commission’s final Carbon Border Adjustment Mechanism (CBAM) rules, adopted in late December 2025, have introduced a pathway that could fundamentally reshape power purchase agreement (PPA) markets in South-Eastern Europe. For the first time, producers of carbon-intensive goods exporting to the EU can materially reduce their CBAM costs by demonstrating the use of physically deliverable, hourly-matched clean electricity. 

CBAM’s definitive phase began on January 1, 2026, transitioning from voluntary reporting to mandatory financial obligations. EU importers must now purchase and surrender CBAM certificates reflecting the carbon content of goods they import, effectively extending the EU’s carbon price to selected imports. 

Understanding CBAM's Definitive Phase

CBAM applies to carbon-intensive goods including cement, iron and steel, aluminum, fertilizers, hydrogen, and electricity. From January 2026, EU importers bringing more than 50 tonnes of CBAM-covered goods must register as authorized declarants and purchase certificates reflecting embedded emissions. 

The mechanism levels the playing field between EU producers—who face carbon costs under the EU Emissions Trading System—and foreign manufacturers who may not. The gradual phase-in aligns with phasing out free ETS allowances for EU producers from 2026 to 2034. 

Certificates for 2026 must be purchased retroactively from February 1, 2027, priced at the average quarterly EU ETS price for 2026. Importers must hold certificates covering at least 50% of year-to-date embedded emissions at each quarter’s end from 2027 onward. 

The PPA Breakthrough

The December 2025 rules introduce a critical provision: importers can reduce CBAM liability by demonstrating that lower-carbon electricity was used in production. Producers may apply an actual emission factor instead of the grid average where electricity is supplied under a PPA. 

However, requirements are stringent. The Commission mandates physical, hourly delivery of electricity. Producers must provide: 

  • Contractual evidence of a PPA directly linking the authorized CBAM declarant to a third-country electricity producer 
  • Coverage of relevant volumes and time periods 
  • A grid diagram showing connection between production site and generation source 
  • Smart meter data confirming electricity delivery within the same hourly measurement period 

Energy attribute certificates play no role, as most systems cannot support robust hourly tracking. Notably, the Commission imposed no asset age restrictions, potentially making a wider range of renewable projects eligible. 

Why South-Eastern Europe Matters

01. The Carbon Intensity Challenge

CBAM costs for Serbian exports are estimated at €1.07 billion for 2023, while the combined figure for Montenegro, Bosnia and Herzegovina, and North Macedonia reaches €797 million. CBAM exports to the EU account for 4-6% of GDP across these countries. 

02. The Export Exposure

CBAM costs for Serbian exports are estimated at €1.07 billion for 2023, while the combined figure for Montenegro, Bosnia and Herzegovina, and North Macedonia reaches €797 million. CBAM exports to the EU account for 4-6% of GDP across these countries. 

Bosnia and Herzegovina and Serbia primarily export electricity, aluminum, and iron and steel to the EU. Serbia, North Macedonia, and Bahrain show high carbon intensity combined with significant export dependence on EU markets. 

03. The PPA Market Gap

PPA activity in these markets remains extremely limited, with only one publicly announced PPA in Serbia in 2023. This creates both challenge and opportunity. 

How PPAs Reduce CBAM Costs

Indirect embedded emissions from electricity are calculated by multiplying electricity consumed with an emission factor based on the country’s electricity mix. For high-carbon grids, this yields substantial CBAM liabilities. 

With a qualifying PPA, producers apply the actual emission factor of the renewable generation source rather than the grid average. 

Consider a Serbian aluminum producer consuming 10 GWh annually. Using Serbia’s grid average emission factor (approximately 650-700 gCO2/kWh), embedded emissions total roughly 6,500-7,000 tonnes CO2. At an EU ETS price of €80-100 per tonne, annual CBAM costs could reach €520,000-700,000. 

With a qualifying PPA from wind or solar (emission factor near zero), the producer virtually eliminates these indirect embedded emissions, saving hundreds of thousands of euros annually while the EU importer avoids purchasing equivalent CBAM certificates. 

The Hourly Matching Requirement

Unlike annual renewable energy certificates matching total annual consumption with generation, hourly matching requires alignment in each hour. This addresses intermittency: when renewables aren’t generating, producers either draw from the grid or rely on storage. 

The CBAM-compliant PPA must ensure claimed electricity is actually covered by the PPA. Implementation requires smart metering infrastructure tracking generation and consumption hourly. The I-TRACK Foundation published a CBAM-compliant I-REC Corporate PPA template with country-specific annexes for markets including Albania, Egypt, Malaysia, Turkey, UAE, and Zimbabwe. 

Challenges and Opportunities

Regulatory and Infrastructure Gaps 

Several obstacles limit PPA development: 

  1. Market Coupling: To achieve CBAM exemption for electricity exports, parties must conduct market coupling with EU member states and introduce carbon pricing mechanisms. Market coupling alone takes 18 months. Only Montenegro-Italy coupling has advanced, expected operational by mid-2026. 
  2. Guarantees of Origin: North Macedonia introduced guarantees of origin in October 2024. Montenegro regulated them in August 2024. Other countries are still developing infrastructure.
  3. Smart Metering: Hourly tracking requires advanced metering infrastructure not widely deployed in industrial facilities. 
  4. Legal Frameworks: PPA contracts require clear frameworks for long-term procurement, grid access, and renewable support areas are still developing. 

Renewable Energy Potential 

Despite challenges, the region possesses substantial resources. IRENA estimates potential for almost 60% renewables in North Macedonia’s power sector by 2030, and 46% for Serbia. Wind and solar projects are increasingly viable as technology costs decline. 

Market Development Pathway 

CBAM PPA opportunity could catalyze market development through: 

  • Anchor Demand: Large exporters facing CBAM costs provide credible, long-term offtake for new renewable projects 
  • Price Signals: Avoided CBAM cost adds value to renewable procurement 
  • Infrastructure Investment: Hourly-matching drives smart metering and tracking infrastructure 
  • Policy Alignment: CBAM compliance accelerates regulatory reforms 
  • Expertise Development: Early transactions build local capacity

Looking Ahead

The Commission’s December 2025 CBAM rules create a compelling economic case for renewable energy procurement in South-Eastern Europe. For producers of carbon-intensive goods exporting to the EU, qualifying PPAs offer a clear route to reducing CBAM costs and maintaining EU market competitiveness. 

For Serbia, Montenegro, and North Macedonia, this demand could catalyze long-dormant PPA markets, accelerate renewable deployment, and support broader energy transition objectives. 

Success requires coordinated action. Industrial companies must assess exposure and engage renewable suppliers. Developers must tailor projects to industrial needs. Governments must accelerate regulatory reforms and infrastructure investments. 

The definitive phase of CBAM has begun. With CBAM costs projected in hundreds of millions of euros annually and substantial renewable potential, the economic logic is clear. The challenge is execution. Building regulatory frameworks, technical infrastructure, and market institutions to turn CBAM’s PPA pathway into a catalyst for South-Eastern Europe’s renewable energy transition. 

First movers are companies and countries establishing functioning PPA markets aligned with CBAM requirements who will gain compounding competitive advantages. The opportunity is now. 

Based on the European Commission’s CBAM implementing and delegated acts published December 2025, effective January 1, 2026. 