Ofgem Demand Connections Reform: What Data Centre Operators Need to Know

Published on 17 June 2026

Himaya Sewwandi - RE24

Himaya Sewwandi
Project Manager

If you are developing a data centre in Great Britain, you have probably felt the grid connection queue tighten like a slow vice. Ofgem’s 16 June 2026 “Connect” update, the latest instalment of its Ofgem Demand Connections Reform programme, is the clearest signal yet of how that queue is about to change. Data centres sit right at the centre of it. 

This is a progress report on the wider Demand Connections Reform programme, with most of the substantive changes still heading to consultation in autumn 2026. But for anyone planning a connection, raising capital, or negotiating terms with a network operator right now, it is essential reading.

Why the Ofgem Demand Connections Reform Exists

The starting problem is simple to state and hard to fix. The connections queue is enormous, much of it will not ever get built, and the well-progressed projects that are viable cannot move fast enough because of network build times and non-viable projects clogging the pipeline. With government and National Energy System Operator (NESO), Ofgem has structured its response around three pillars, Curate, Plan, and Connect. This update covers the third. 

Ofgem is explicit that data centres “must be central to any solutions,” given the scale and pace of their demand growth and the distinct way they are financed and built. This is not generic grid policy with data centres mentioned in passing. The reform is being shaped substantially around data centre characteristics, which means whatever lands in autumn will likely define your connection options for years. 

One telling data point buried in the document. Ofgem has identified roughly 117 active applications to the gas network, which it attributes mainly to data centres trying to get operational ahead of electricity connection delays. That is the clearest evidence yet of how acute the queue pressure has become.

Self-Build: The Demand Connections Reform's Biggest Practical Shift

The Connect Accelerate workstream is where the most concrete near-term change is happening. Ofgem is moving away from simply clarifying existing law (it concluded that interpreting the Electricity Act 1989 would not give developers the certainty they need) and toward creating new structural options instead. Two are being developed in parallel. 

A class exemption, which would let certain project types own high-voltage assets without a full transmission licence. Ofgem is working through which project types should qualify. 

An independent transmission owner (iTO) licence, modelled loosely on the existing iDNO licence for distribution. Ofgem is treating this as the priority option, since stakeholders want a standardised, predictable licence rather than a one-off, case-by-case negotiation each time. 

To work out which option suits which kind of project, Ofgem and its Connect Task and Finish Group have built four project archetypes. These archetypes are ranging from a single data centre with its own substation, through to multi-customer sites sharing generation and storage via a “GridCo” special purpose vehicle. If you are scoping a self-build strategy, mapping your project against these archetypes now will save you time once the autumn consultation lands. 

There is also a quieter but materially important change. High voltage connection offers, already available in Scotland, are being extended to England and Wales. For data centres large enough to step down their own voltage, that removes a real structural barrier that’s existed for years. 

This includes extending “contestable build” arrangements, which allow private parties to construct elements of the network. At present, this is only permitted in limited circumstances.  The proposed change would expand its application to include high-voltage assets as well. These changes are being introduced under powers in the Planning and Infrastructure Act. The Irish precedent Ofgem cites is striking. Projects built contestably there have come in roughly 20% cheaper and 11 months faster. If GB achieves anything close to that, it is a genuine commercial advantage worth planning around.

Operate: Where the Demand Connections Reform's Real Trade-offs Sit

If Accelerate is about how you build, Connect Operate is about how you are allowed to run once you are connected. 

Ofgem frames this as a three-way trilemma between system needs (variable, risk borne by consumers), data centre operational needs (site- and business-model-specific), and data centre investability needs (additional requirements create financing risk). Three measures are on the table: 

Alternative connection agreements. Including a proposed “N-1 connection” that deviates from standard security requirements, and phased connection agreements where capacity ramps up over years rather than arriving all at once. Phasing in particular aligns naturally with how data centres actually scale, and could let you connect in parallel with wider network upgrades rather than waiting for them to finish first. 

Voluntary flex services. Incentivising data centres to operate flexibly in exchange for faster or larger connections. Ofgem acknowledges flexibility potential varies hugely by data centre type (AI training loads are more flexible than steady-state cloud workloads), and a new Flex Technical Taskforce, launching late June 2026 and reporting to the newly formed AI Energy Council, will dig into what’s realistically achievable site by site. 

Operational control measures. This is the backstop. Potentially mandatory curtailment during system stress events, designed to let Ofgem take on more connection risk without compromising security. Industry feedback has already flagged this as a real bankability concern, and Ofgem acknowledges the tension directly. Greater voluntary uptake of flexibility reduces the need for this backstop. So there is a genuine incentive alignment here worth understanding before you negotiate connection terms.

What this Means if You are Building Now

The honest summary of this Ofgem Demand Connections Reform update is, nothing is decided yet, but the direction is now unmistakable. Expect formal consultations in autumn 2026 covering the iTO licence, self-build and transfer code modifications, connection agreement options, and operational control measures timed to land before the next connections window opens (expected Q4 2026). 

For data centre developers, the practical takeaway is to treat this as a planning input now, not a wait-and-see document. Map your project against Ofgem’s four archetypes. Start thinking concretely about how much flexibility your operation could realistically offer, because that number will directly shape your negotiating position once voluntary flex services and operational control measures move from concept to consultation.  

The reform will not simplify your connection journey by itself. But understanding where Ofgem is heading and why data centres are driving so much of that direction gives you a real head start on the operators who wait for the consultation paper to land before reading the room. 

RE24 will continue tracking developments in the Ofgem Demand Connections Reform process through autumn 2026, including the iTO licence consultation and Flex Technical Taskforce findings. Get in touch if you’d like to talk through how hourly-matched, flexible clean power procurement fits into your connection strategy.